CentraCare Construction Update

23 Feb 2017


Healthcare

CentraCare Update

CentraCare Update Overhead

CentraCare Aerial

Medical Campus Site

  • Clinic area is being roughed-in with plumbing and electrical.
  • Operating Rooms are being sheet-rocked.
  • Nichiha panels being installed on south side of building.
  • Main entry stone work is nearing completion.

Assisted Living Site

  • Rough-ins for wings B and C are almost complete.
  • Insulation is being installed and sheet rock will start soon.
  • Exterior finishes will start next week.
  • Roof is complete.